How Much Would High Speed Rail Actually Cost? (2024)

How Much Would High Speed Rail Actually Cost? (1)

Earlier this year, Seattle Transit Blog covered possible routes for high-speed rail (HSR) to Vancouver. Zach Shaner wrote the first two parts, and I wrote the last two. In December, Washington State DOT (WSDOT) released a study about the possibility of HSR in the Pacific Northwest. The study is bearish on HSR, with high cost estimates and unusually low operating performance—but the numbers themselves are suspect, suggesting a unit conversion error. WSDOT says that the numbers in the study are right—but there is cause for skepticism. If the numbers are wrong, the entire study must be redone, and would point to a more positive conclusion about the prospects of HSR.

The Error

The source of the unit conversion error involves miles and kilometers. A mile is about 1.6 kilometers, so the cost per mile of anything is by definition 1.6 times the cost per kilometer. On table 5-10 of the study, there are cost ranges for various items. The original costs per kilometer were instead 1.6 times higher than the costs per mile. It is the costs per mile in the study that are correct. Thus, the study’s costs per kilometer were inflated by a factor of 2.6: instead of dividing by 1.6, the study’s authors multiplied by 1.6, and 1.6 squared is about 2.6.

When I pointed the unit conversion error, WSDOT rail division communications manager Janet Mankin said, “That conversion appears to be the only error. All of the capital and operating costs and costs recovery numbers were calculated based on cost per mile.” Since then, the table was corrected, and the costs per kilometer are now correct. Unfortunately, it appears what Mankin said was incorrect, and the cost estimates elsewhere used the inflated numbers, overstating the costs of HSR in the Pacific Northwest by a factor of 2.6.

The telltale sign is operating costs. The study believes that HSR in the Pacific Northwest will only be able to recover 62-83% of operating and maintenance costs through fares (table 5-1). This is a red flag: internationally, HSR makes money. The profits of the Japanese Shinkansen operators, and of the long-distance divisions of the French and German national railways, speak for themselves; even Taiwan HSR, which made news for going bankrupt, always had operating profits, and was weighed down by interest rates on construction debt.

The operating and maintenance costs in table 5-1 are a range of $0.65-0.78 per passenger-mile. This contrasts with costs given in table 5-10 of $0.09 per seat-mile, about 12-13% occupancy: WSDOT’s numbers assume the trains will be practically empty. But table 5-5 gives a maximum train load of about 30%; with nearly all ridership coming from the major stations, trains are likely to be at close to their maximum load the entire way. The difference between 12% and 30% occupancy is very close to the 2.6 factor of the unit conversion error.

When I reached out to study consultant Scott Richman, he defended the numbers, saying that the model they come from is separate from the model used in table 5-10. He also said he sent an explanation written by study consultant group AECOM to WSDOT, but as of the time this post goes to press (the evening of January 8th) the study has not been updated with any such information. Without additional information, the evidence suggests that the study used the wrong numbers.

The good news is that fares are likely to cover much more than just the operating and maintenance costs (certainly more than the study’s 62-83% range). This makes HSR a better value proposition; if the numbers in the study are correct, then HSR is too cost-ineffective.

The Problem with the Model

The study uses a coarse model to evaluate ridership, called CONNECT. The model cannot evaluate ridership within each metropolitan area, only between different metro areas. Thus, it cannot distinguish the various alignment options proposed: from its point of view, a downtown station and a station at the edge of the metro region are equivalent. Richman explained that the model actually sandbags downtown stations, by including a special fudge factor boosting ridership at airport stations; this makes the option of serving Vancouver at the airport rather than at Pacific Central Station look better.

The study’s main alternatives do not even go into city centers. Of the three alternatives analyzed for operating costs, one (Alternative 1A) has an airport station in Vancouver rather than a downtown station, one (2) has an airport station in Portland, and one (4) has peripheral stations in all three major cities.

The study recognizes its own model’s limitations. It calls for further investigation of alternatives including downtown versus peripheral stations, and options with or without stations in intermediate cities such as Bellingham and Everett. But if the alternatives proposed are the ones progressing to the next level of analysis, then the entire process will be compromised because of the weakness of CONNECT.

How High are Construction Costs?

The study says that the capital cost range is $24-42 billion in 2017 dollars, or about $80-140 million per mile. This is almost certainly too high, for two separate reasons.

The first reason is that the capital costs may have the same unit conversion error as operating costs. Without seeing the AECOM response, it is impossible to tell what went into the capital cost model. If this is what happened, then the correct figure is most likely $9-16 billion, which is much easier for the state to afford (and in line with French TGV construction costs).*

The second reason is that the study says that all alternatives are assumed to include heavy tunneling. The reason given is “to not preclude any technologies at this stage,” including Hyperloop: in other words, this study is using Hyperloop and maglev tunneling requirements to analyze conventional HSR, which can use legacy rail rights-of-way to complete the last few miles into Vancouver, Seattle, and Portland at relatively low cost.

Based on the assumption that heavy tunneling is needed no matter what, the study finds very little difference in capital cost between HSR and maglev. This is not what railroads choosing what to build have found: maglev technology cannot use legacy tracks and must tunnel to reach city centers, driving the high cost of the only intercity line under construction today, the Chuo Shinkansen between Tokyo and Osaka.

HSR at Lower Cost

It is almost certain that both capital and operating costs for HSR in the Pacific Northwest are affordable, contrary to what the WSDOT study found.

If the operating ratio is only 62-83%, then the best way to maintain good finances is to run as few trains as possible; when operating costs are averaged out with capital costs, the study finds that the optimum is only about 15 roundtrips per day.

But in reality, HSR operating ratios are much more than 100%. With the operating costs reduced to correct the unit conversion error, the operating ratio should be 160-215%, which means that it’s best to run as many trains as can be filled, to help pay off construction costs using operating profits.

With lower operating costs, HSR service could also charge lower fares. The assumption on fares is very high: $0.50 per passenger-mile, as compared with about $0.35 on the Shinkansen and $0.20 on French and German intercity trains. Reducing the fare to European levels would raise ridership, allowing trains to run fuller and more frequently: German intercity trains averaged a 60% load factor in 2016.

If the costs are what the WSDOT study says they are, then the process should stop here: HSR in the Pacific Northwest is too expensive to build and operate. But if the costs are lower, then it could provide much more than the limited options the study suggests. Trains could connect Seattle with Vancouver in 1:10 and with Portland in 1:20, every half hour, charging $30, and making a profit.

*Editors’ Note: CAHSR Phase 1 will cost $123m/mile, but that is in Year of Expenditure (YOE) dollars. When expressed in 2017 dollars, this study assumes a cost considerably higher than California’s.

How Much Would High Speed Rail Actually Cost? (2024)

FAQs

How Much Would High Speed Rail Actually Cost? ›

This network would cost around £32 billion to construct (in 2009 prices) – revised costs for HS2 are detailed in the Economic Case for HS2: Updated Appraisal of Transport User Benefits and Wider Economic Benefits – and would deliver very significant benefits for rail travellers, including unprecedented increases in ...

How much will the high-speed rail line cost? ›

The cost of building the entire High Speed 2 (HS2) network is estimated to be in the region of £100bn. The funding envelope for phase one alone is up to £44.6bn. It means building HS2 will cost around £200M per kilometre.

Why does HS2 cost so much? ›

For instance, engineers discovered that ground conditions were poorer than HS2 Ltd. had expected, necessitating more structural work before laying the tracks. The cost of civil engineering for Phase 1 rose £5bn between 2017 and 2019, accounting for almost half of the cost increase on this part of the line.

How much would Hyperloop cost vs high-speed rail? ›

Modelling by Virgin Hyperloop One in 2016 estimated a per-mile cost of $84 to $121 million for a cut-down 107-mile Bay Area project. This compares to a projected cost of $178 million per mile for the full Californian high speed rail project.

How much does the high speed train cost in the UK? ›

Even before Britain's run of double-digit inflation from late 2022 to early 2023, the HS2 budget had ballooned. Its 2015 cost of 55.7 billion pounds ($68 billion) reached 98 billion pounds by 2019, and a 2020 review showed that could rise to 106 billion pounds.

Why is UK rail so expensive? ›

The reasons for this are varied: from the privatisation of the rail industry to the rising cost of infrastructure. The UK does not have fixed rates like other European countries such as France, which can result in flight tickets being cheaper than a regional train journey in the UK.

Will the UK get high-speed rail? ›

High Speed 2 (HS2) is a planned high-speed railway line in England, which will run between Manchester and London with branches to Birmingham and the East Midlands, near Nottingham. HS2 will be Britain's second purpose-built high-speed line, the first being High Speed 1, which connects London to the Channel Tunnel.

Is HS2 good value for money? ›

However, by including wider economic impacts such as agglomeration effects – the productivity gains from people and companies relocating in response to better transport – HS2 remains medium value-for-money.

How much is HS2 costing in total? ›

The cost of completing HS2 has ballooned from £33bn a decade ago to an estimated £100bn today, making the project “a sitting duck for cuts,” said New Civil Engineer.

How much has HS2 already cost? ›

How much has HS2 cost so far? The original cost of HS2 – at 2009 prices – was supposed to be £37.5 billion. In 2020, the leaked Oakervee Review revealed the total project could cost up to £106.6bn, but concluded “on balance” it should continue.

Is Hyperloop cost effective? ›

According to preliminary estimates, the hyperloop is expected to be 2 to 3 times more energy-efficient than its counterpart, HSR. Musk (2013) underlines that the technology will be self-sustaining and cost-effective due to a low energy demand system powered by solar energy.

Is Hyperloop really feasible? ›

While Elon Musk's Hyperloop is physically possible, it faces tremendous engineering obstacles. Major tradeoffs will involve cost, safety, and practicality. Any accidents, such as an air leak, would be catastrophic.

How much does 1 mile of Hyperloop cost? ›

Hyperloop One estimated that for a loop around the Bay Area the costs were in a range on $9 billion to $13 billion in total, or from $84 million to $121 million per mile.

Are UK trains the most expensive? ›

The UK is the most expensive country by far in terms of single travel with tickets booked on the day of the journey. You would pay £30 (€33.90) to travel from London's Paddington Station to Oxford.

Did train prices go up UK? ›

It is not known what next year's increase will be, but this year the government increased national rail fares by 5.9%, which was well below July 2022's RPI figure of 12.3%. That increase was still the largest since 2012, according to regulator the Office of Rail and Road.

How much does a high speed train driver earn in the UK? ›

The average train driver salary in the UK is £48,500 per year. Train drivers can expect to begin with an average starting salary of £30,000, with the highest salaries often exceeding £65,000. Train driver salaries can also differ between commercial or freight roles.

How much will the high-speed rail cost China? ›

"It costs 120 million to 130 million yuan to extend the high-speed rail 1 km," he estimates. This suggests that extending the network by 8,000 km by 2025 would take an investment on the scale of 1 trillion yuan. In terms of total passenger traffic, a target of 2.69 billion passengers has been set for 2023.

How much will the city rail link budget? ›

The cost of Auckland's City Rail Link - New Zealand's largest ever transport project - has blown out by over $1b more due to Covid-19 lockdowns and other revised costs. The project's cost is now estimated to be $5.493b - a $1.074b increase on the previous estimate of $4.419b.

How much will the maglev line cost? ›

Central Japan Railway (JR Central) has announced that it expects its 290km ultra-high-speed maglev line between Tokyo and Nagoya to cost $64bn, a rise of almost $14bn on the original cost estimate.

How much did the express rail link cost? ›

Construction of the railway line has cost the Hong Kong government HK$86.4 billion, after the number gradually rose from the initial estimate of HK$66.9 billion.

Top Articles
Latest Posts
Article information

Author: Rev. Porsche Oberbrunner

Last Updated:

Views: 6521

Rating: 4.2 / 5 (53 voted)

Reviews: 84% of readers found this page helpful

Author information

Name: Rev. Porsche Oberbrunner

Birthday: 1994-06-25

Address: Suite 153 582 Lubowitz Walks, Port Alfredoborough, IN 72879-2838

Phone: +128413562823324

Job: IT Strategist

Hobby: Video gaming, Basketball, Web surfing, Book restoration, Jogging, Shooting, Fishing

Introduction: My name is Rev. Porsche Oberbrunner, I am a zany, graceful, talented, witty, determined, shiny, enchanting person who loves writing and wants to share my knowledge and understanding with you.